Intelligent Planning/Tools/Contractor Progress Roll-UpTalk to us →

Contractor Progress Roll-Up ALPHA

You hold a summary (L2) programme; your contractor holds a detailed (L3/4) one, progressed to their data date. Map each of your activities to a date span in their programme (two anchor activities) and this tool derives your percent complete, actual start, and a calendar-corrected remaining duration so your activity lands on the contractor's dates, through an accept/reject review, with an auditable report and an updated XER.

🔒 Both files are parsed in your browser and never uploaded.

1 · Load schedules

Your XER and the contractor's are required. Baselines are optional and drive the integrity checks.

My schedule (L2) *
client XER, drop or click
Contractor schedule (L3/4) *
progressed XER, drop or click
My baseline (optional)
for integrity checks
Contractor baseline (optional)
for integrity checks

Why a calendar correction?

P6 derives dates from remaining duration on each activity's own calendar when you schedule (F9). Your summary activity and the contractor's detail often run on different calendars: a 5-day/8-hour week versus a 6-day/10-hour one. The same finish date is a different number of working hours on each. This tool computes the remaining duration in your calendar so that scheduling from your data date lands your activity on the contractor's date, rather than copying a duration number that would put it weeks out.

More Primavera P6 tools