Schedule Mentor
Nobody teaches you this. Load your Primavera P6 schedule and get a friendly, patient review, not a pass/fail audit, that explains what to fix, why it matters, and exactly how to do it in P6, using examples from your own file.
What we’ll look at together
A guided walkthrough, one idea at a time, at your pace. These are the exact things juniors search for:
- Logic: open ends, danglers, negative lag (leads), Start-to-Finish links, lag hygiene, the FS mix.
- Constraints: mandatory dates that hide slip, and constraints doing a relationship’s job.
- Calendars & durations: calendar mix on a chain, long activities, milestone/zero durations.
- Progress: the data date as the line between history and forecast; the 50% smell.
- Structure: WBS shape, Activity ID room-to-insert, naming, and what huge float really means.
Ready for a formal score afterwards? Run the DCMA 14-point assessment. This is the friendly version that explains the metrics.