Schedule Risk Analysis, screening grade
A Monte Carlo simulation of your Primavera P6 network, in the browser. It answers one question honestly: how much confidence does your deterministic finish date actually deserve, and which activities drive the risk?
🔒 Your file is parsed in your browser and never uploaded.
1 · Load & validate
Before simulating, the engine reproduces your deterministic schedule and checks it against the XER’s own dates. A simulation on an engine that can’t match the plan is noise.
2 · Ranges & settings
Review grid, every incomplete activity and the range it will simulate with
3 · Results
What am I looking at? (S-curve & P-values)
The S-curve is the cumulative probability of finishing by each date. P80 means an 80% chance of finishing on or before that date. Your deterministic plan date usually lands low (often ~P20–P40) because of merge bias: where two paths join, the later one wins, so parallel risk only ever pushes the date out, never in.
Criticality vs cruciality?
Criticality index = how often an activity sits on the critical path across iterations. Sensitivity/cruciality = how strongly an activity’s sampled duration correlates with the finish date. High criticality + high sensitivity = a true risk driver.