How to use XER Logic Network

This guide is for planners. It covers getting the right files out of Primavera P6, what each part of the tool tells you, and, most importantly, how to judge whether a result is real and what to do about it.

Open the tool   The tool also has a short on-screen tour: press Take the tour.

Contents
  1. Preparing and loading your files
  2. Checking what was read
  3. Choosing the start and the end
  4. The network view
  5. Pinch points: reading, reviewing and fixing
  6. Predecessors
  7. Configuration states
  8. Saving, exporting and limits
  9. Glossary

1. Preparing and loading your files

Before you export from P6

Loading

Drop the files on section 1, or press the box to choose them. You can add more later. Files are read in your browser and are never uploaded. If names or pound signs look garbled, change that file's Encoding in the table.

No files to hand? Press Load the sample programme: an invented rail upgrade in two linked projects.

2. Checking what was read

FigureWhat it meansWhat to do
Activities and linksEverything read, including completed work.Compare with P6. A big difference means a project is missing from the export.
LoopsA chain of logic that leads back to itself.P6 will not schedule a project with a loop, so check the file was scheduled and look at loops that cross files. Open the list to see each one.
Unresolved external linksLogic to an activity that is not in any loaded file.Load the other project. If it is not available, treat results near those links with care.

Links between projects

When you export one project, P6 includes stand-in copies of the activities it links to in other projects. The tool does not count them as activities. If you load the other project as well, the link joins the real activity; if not, it is listed as unresolved with its Activity ID.

Match external links by Activity ID is for files that come from different P6 databases. Tick it only if the same activity carries the same Activity ID in both. It never joins an activity to one in its own project, and it reports any ID that is used more than once.

3. Choosing the start and the end

Everything about pinch points depends on this choice. The end is the thing the work is leading to. The scope is every activity on at least one chain of logic from a start to that end.

Choosing the end

Starts

Leave the start empty to include every route that begins at an activity with no predecessor. Choose a start (for example contract award or access to site) to see only the routes from there.

Completed work

Completed activities are left out unless you tick Include completed activities. With them left out, every activity whose predecessors are all complete becomes a new start of the remaining logic, so a statused programme can have many starts. That is right for "what drives the end from here", and the shares will differ from an unprogressed view. Tick the box to see the whole job.

Critical definition

Choose total float at or below a number of days (0 by default) or P6's longest path flag. Reset scope puts the start, end and definitions back to the beginning without touching your files or configuration points.

4. The network view

5. Pinch points: reading, reviewing and fixing

What the share means

The tool counts every separate route of logic from a start to your end. An activity's share is the percentage of those routes that go through it.

Start leads to A and B, which both lead to M. M leads to C and D, which both lead to End. Start also leads to F, which leads to End. StartABMCDFEnd
Five routes run from Start to End. Four pass through M, so its share is 80%. A, B, C and D each carry 40%, F carries 20%, and Start and End are on every route (100%).
What it is not. A share is a count of routes in the logic. It is not a probability, not float, not criticality and not a measure of risk by itself. An activity can be on 100% of routes and have months of float. Use the list to decide where to look.

A single point is on every route: remove it and no chain of logic joins your starts to your end. Merge is the number of direct predecessors, Burst the number of direct successors, and Upstream and Downstream count all the work before and after it.

If the list is empty or very short

What you seeWhyWhat to do
"Choose the end activity"No end has been picked yet.Press Use beside the right milestone.
Only a handful of rowsThe chosen end has little work behind it.Choose another end, or find the missing logic into it.
No rowsThe logic spreads over many routes, or a filter is hiding rows.Lower the share to 5%, or set the filters back to all.
No path at allLogic is broken between start and end, or the chosen point is completed.Include completed activities, clear the start, or trace the predecessors of the end to find the gap.

How to review a pinch point

Work down the list from the top with Next. For each one, ask: is there a real reason all this work has to pass through here?

  1. Name it. Is it a physical gate (access, possession, structure complete), a contractual one (approval, consent, handover), or a shared resource? If you can name it, it is probably genuine.
  2. Look at what comes in. In the tool, select it and choose Direct predecessors only on the Predecessors tab; in P6 open the activity's Relationships. Would each predecessor really stop this activity?
  3. Look at what goes out. Does each successor really need this activity, or only something earlier?
  4. Check the dates and float. A high share with low or negative float deserves attention first.
  5. Challenge it with the delivery team. Ask what would happen if this activity were a month late. If the honest answer is "not much", the logic is wrong.

Common causes that are not real

PatternHow to spot itHow to fix it in P6
Collector milestone used as a hubA milestone with many predecessors and many successors, such as "Design complete".Link each successor to the particular work it needs. Keep the milestone for reporting, fed by logic but not driving everything after it.
Redundant linksA links to C, and also to B which links to C.Remove the link that adds nothing. This changes route counts as well as tidying the logic.
Everything linked to one start or one admin activityAn early activity near 100% that is not a real gate.Replace with the true prerequisites of each piece of work.
Dangling start or finishOnly start-to-start predecessors, or only finish-to-finish successors, so part of the activity drives nothing.Give the start a predecessor and the finish a successor that mean something.
Constraint doing the job of logicA date constraint holds the activity and little feeds it.Add the real predecessor and remove or justify the constraint.
Open endsWork with no successor never reaches your end, so it is missing from the counts.Link it to the activity that needs it. The tool's Open ends figure and the floating list on the Configuration states tab help to find them.
LoopsListed in section 2.Break the loop at the link that is wrong. The tool sets one link aside only so that it can count.
Level of effort or summary activitiesAppear only if you ticked the box.Leave them excluded: they span work and distort logic.

Close the loop

  1. Agree the change with whoever owns the logic and record why.
  2. Change it in P6, schedule (F9) and read the schedule log.
  3. Check that dates and float moved only as you expected.
  4. Export again, load the new file, and load your saved settings to compare like with like.

A genuine pinch point is not a fault. Record it, give it an owner, protect its float and watch its predecessors.

6. Predecessors

This answers "what has to happen before this?" Choose an activity (typically a milestone) to list everything upstream of it through any chain of logic, including other projects.

If something you expect is missing, there is no chain of logic from it to your activity. That is usually the most useful finding of all.

7. Configuration states

A configuration state is the work needed to reach one point that has not already been counted for an earlier one. With points X, Y and Z in order: state X is X and everything before it; state Y is Y and everything before it, less state X; state Z is what is left upstream of Z. Each activity lands in one state only.

Choosing the points

Reading the checks

MessageMeaningAction
Point is upstream of an earlier point (error)It already happens before a point listed above it, so the order is wrong.Move it up with the arrows. No states are calculated until this is fixed.
Point is not downstream of the previous point (warning)No chain of logic leads from one to the next.Either they are parallel, which is acceptable if intended, or logic is missing.

Floating work

"Floating" here is about logic only. It has nothing to do with total float.

8. Saving, exporting and limits

9. Glossary

ScopeActivities on at least one chain of logic from a start to an end.
Route or pathOne chain of relationships from a start to an end.
Pinch pointAn activity that a large share of routes pass through.
Single pointAn activity on every route.
Open endAn activity with no predecessor or no successor.
PredecessorAnything upstream through logic, whether directly or through other activities.
Configuration stateThe work belonging to one configuration point and to no earlier one.
Unresolved external linkLogic to an activity that is not loaded.