How to use XER Logic Network
This guide is for planners. It covers getting the right files out of Primavera P6, what each part of the tool tells you, and, most importantly, how to judge whether a result is real and what to do about it.
Open the tool The tool also has a short on-screen tour: press Take the tour.
1. Preparing and loading your files
Before you export from P6
- Schedule the programme (F9) so that dates and float are current. The tool uses what P6 exported and never recalculates it.
- Read the schedule log while you are there. It lists open ends, constraints and out-of-sequence progress, which all affect what you will see here.
- Export linked projects together (File, Export, XER) by selecting all of them in one export, or export each one and load all the files here.
- Do not load two updates of the same project at once. The tool warns you if it sees the same project twice.
Loading
Drop the files on section 1, or press the box to choose them. You can add more later. Files are read in your browser and are never uploaded. If names or pound signs look garbled, change that file's Encoding in the table.
No files to hand? Press Load the sample programme: an invented rail upgrade in two linked projects.
2. Checking what was read
| Figure | What it means | What to do |
|---|---|---|
| Activities and links | Everything read, including completed work. | Compare with P6. A big difference means a project is missing from the export. |
| Loops | A chain of logic that leads back to itself. | P6 will not schedule a project with a loop, so check the file was scheduled and look at loops that cross files. Open the list to see each one. |
| Unresolved external links | Logic to an activity that is not in any loaded file. | Load the other project. If it is not available, treat results near those links with care. |
Links between projects
When you export one project, P6 includes stand-in copies of the activities it links to in other projects. The tool does not count them as activities. If you load the other project as well, the link joins the real activity; if not, it is listed as unresolved with its Activity ID.
Match external links by Activity ID is for files that come from different P6 databases. Tick it only if the same activity carries the same Activity ID in both. It never joins an activity to one in its own project, and it reports any ID that is used more than once.
3. Choosing the start and the end
Everything about pinch points depends on this choice. The end is the thing the work is leading to. The scope is every activity on at least one chain of logic from a start to that end.
Choosing the end
- When files load, the tool offers a short list of likely milestones with the number of activities that feed each. Nothing is calculated for pinch points until you pick one.
- Usually you want completion, entry into service or a key contractual milestone.
- The latest-finishing milestone is often not the right one: a follow-on or reporting milestone can finish last and have very little behind it. If the number feeding it is small compared with the programme, choose another.
- You can search for any activity under End activities, and choose several (for example all section completions).
- If the milestone you expected has little behind it, that is a finding: logic is probably missing between the work and the milestone.
Starts
Leave the start empty to include every route that begins at an activity with no predecessor. Choose a start (for example contract award or access to site) to see only the routes from there.
Completed work
Completed activities are left out unless you tick Include completed activities. With them left out, every activity whose predecessors are all complete becomes a new start of the remaining logic, so a statused programme can have many starts. That is right for "what drives the end from here", and the shares will differ from an unprogressed view. Tick the box to see the whole job.
Critical definition
Choose total float at or below a number of days (0 by default) or P6's longest path flag. Reset scope puts the start, end and definitions back to the beginning without touching your files or configuration points.
4. The network view
- Timeline places activities by start date in lanes by WBS, project or configuration state. WBS overview shows one dot per WBS element; click one to open it. Free draws a network map and is best on a few thousand activities.
- Show narrows the picture to the scope, the critical work, or a few logic steps around the selected activity.
- Colour by float band, configuration state, project or pinch score.
- Click an activity: blue lines are its predecessor logic, green its successor logic. Click empty space or press Escape to clear.
- Reset view clears the selection and puts every view choice back to normal.
5. Pinch points: reading, reviewing and fixing
What the share means
The tool counts every separate route of logic from a start to your end. An activity's share is the percentage of those routes that go through it.
A single point is on every route: remove it and no chain of logic joins your starts to your end. Merge is the number of direct predecessors, Burst the number of direct successors, and Upstream and Downstream count all the work before and after it.
If the list is empty or very short
| What you see | Why | What to do |
|---|---|---|
| "Choose the end activity" | No end has been picked yet. | Press Use beside the right milestone. |
| Only a handful of rows | The chosen end has little work behind it. | Choose another end, or find the missing logic into it. |
| No rows | The logic spreads over many routes, or a filter is hiding rows. | Lower the share to 5%, or set the filters back to all. |
| No path at all | Logic is broken between start and end, or the chosen point is completed. | Include completed activities, clear the start, or trace the predecessors of the end to find the gap. |
How to review a pinch point
Work down the list from the top with Next. For each one, ask: is there a real reason all this work has to pass through here?
- Name it. Is it a physical gate (access, possession, structure complete), a contractual one (approval, consent, handover), or a shared resource? If you can name it, it is probably genuine.
- Look at what comes in. In the tool, select it and choose Direct predecessors only on the Predecessors tab; in P6 open the activity's Relationships. Would each predecessor really stop this activity?
- Look at what goes out. Does each successor really need this activity, or only something earlier?
- Check the dates and float. A high share with low or negative float deserves attention first.
- Challenge it with the delivery team. Ask what would happen if this activity were a month late. If the honest answer is "not much", the logic is wrong.
Common causes that are not real
| Pattern | How to spot it | How to fix it in P6 |
|---|---|---|
| Collector milestone used as a hub | A milestone with many predecessors and many successors, such as "Design complete". | Link each successor to the particular work it needs. Keep the milestone for reporting, fed by logic but not driving everything after it. |
| Redundant links | A links to C, and also to B which links to C. | Remove the link that adds nothing. This changes route counts as well as tidying the logic. |
| Everything linked to one start or one admin activity | An early activity near 100% that is not a real gate. | Replace with the true prerequisites of each piece of work. |
| Dangling start or finish | Only start-to-start predecessors, or only finish-to-finish successors, so part of the activity drives nothing. | Give the start a predecessor and the finish a successor that mean something. |
| Constraint doing the job of logic | A date constraint holds the activity and little feeds it. | Add the real predecessor and remove or justify the constraint. |
| Open ends | Work with no successor never reaches your end, so it is missing from the counts. | Link it to the activity that needs it. The tool's Open ends figure and the floating list on the Configuration states tab help to find them. |
| Loops | Listed in section 2. | Break the loop at the link that is wrong. The tool sets one link aside only so that it can count. |
| Level of effort or summary activities | Appear only if you ticked the box. | Leave them excluded: they span work and distort logic. |
Close the loop
- Agree the change with whoever owns the logic and record why.
- Change it in P6, schedule (F9) and read the schedule log.
- Check that dates and float moved only as you expected.
- Export again, load the new file, and load your saved settings to compare like with like.
A genuine pinch point is not a fault. Record it, give it an owner, protect its float and watch its predecessors.
6. Predecessors
This answers "what has to happen before this?" Choose an activity (typically a milestone) to list everything upstream of it through any chain of logic, including other projects.
- Uses: a readiness review before a milestone, an assurance check of what the date rests on, or finding logic that should not be there.
- Links back is the shortest number of relationships between the row and your activity. 1 is a direct predecessor.
- Direct successors in this list shows what each row feeds on the way to your activity, with relationship type and lag.
- Filters: start with Direct predecessors only, then widen. Not completed with Critical only gives the work most likely to need attention. Click any column heading to sort.
- Anywhere or within scope: "within scope" keeps only activities that are also in the section 3 scope.
- Download Excel saves the list as filtered, with a cover sheet saying how it was filtered. Add activity code columns first if you want to group by discipline or contractor.
If something you expect is missing, there is no chain of logic from it to your activity. That is usually the most useful finding of all.
7. Configuration states
A configuration state is the work needed to reach one point that has not already been counted for an earlier one. With points X, Y and Z in order: state X is X and everything before it; state Y is Y and everything before it, less state X; state Z is what is left upstream of Z. Each activity lands in one state only.
Choosing the points
- Pick moments when the asset or job is in a defined, describable condition: access granted, structure complete, power on, section handed over, entry into service.
- Use milestones that are properly driven by logic. Check each with the Predecessors tab: if little feeds it, fix that first.
- List them in the order they happen. Each should normally be downstream of the one before.
- Start with three to six points. Add more when the picture is sensible.
- Give each a short name: it is used in the network, the lanes and the Excel sheets.
Reading the checks
| Message | Meaning | Action |
|---|---|---|
| Point is upstream of an earlier point (error) | It already happens before a point listed above it, so the order is wrong. | Move it up with the arrows. No states are calculated until this is fixed. |
| Point is not downstream of the previous point (warning) | No chain of logic leads from one to the next. | Either they are parallel, which is acceptable if intended, or logic is missing. |
Floating work
- Isolated: no relationships at all. Nearly always needs logic or removing.
- Not feeding any configuration point: open ends, chains that stop short, and work after your last point. Review it: add the missing successor, add a later point, or accept it as post-completion work.
"Floating" here is about logic only. It has nothing to do with total float.
8. Saving, exporting and limits
- Save settings keeps your ends, thresholds, points and view choices in a small file, by Activity ID. Load it with next month's export.
- Excel downloads sit with each list. PNG, SVG and PDF (A3 or A1) save the network as shown on screen.
- Large programmes get a warning before anything slow, and you can cancel. Very large workbooks may be slow to open.
- Nothing is stored: closing or refreshing the page forgets your files.
- The tool does not recalculate dates or float, and it does not read baselines: "Planned" dates are P6's target dates.
- This is an alpha release. Check important results against P6.
9. Glossary
| Scope | Activities on at least one chain of logic from a start to an end. |
|---|---|
| Route or path | One chain of relationships from a start to an end. |
| Pinch point | An activity that a large share of routes pass through. |
| Single point | An activity on every route. |
| Open end | An activity with no predecessor or no successor. |
| Predecessor | Anything upstream through logic, whether directly or through other activities. |
| Configuration state | The work belonging to one configuration point and to no earlier one. |
| Unresolved external link | Logic to an activity that is not loaded. |