Blog

Tool launches and updates

What we have added to our Primavera P6 and planning tools, and why. Every tool runs in your web browser: your files stay on your computer and are never uploaded.

Time-Chainage Chart: now a proper drawing, with clashes marked

The chart now reads like a traditional time-location diagram: round-number axes, labels, stations and structures, progress, clashes and a title block, ready to print at A3 or A1.

The first version drew lines and little else. This update turns it into something you can put on a wall or in a meeting pack, without a licence for a specialist package.

  • It finds the From and To chainage fields for you when you load a file.
  • Axes use round numbers and calendar months, with the year, week lines and a labelled data date.
  • Work is drawn in the right shape: lines for crews moving along the route, boxes for possessions and compounds, bars for structures and diamonds for milestones. Activities with no chainage have their own strip instead of being dropped.
  • Labels sit along each line and skip a spot rather than overlap. Runs of the same crew with the same rate become a single label such as “Track Install, 54 m/d”.
  • A location strip shows stations, structures and sections along the route. Edit it, or paste your own from Excel.
  • Shade a shutdown, a sensitive stretch of land or a possession. Completed work is drawn paler, and work in progress is split at the data date.
  • Clashes, where two crews from different groups would be in the same place at the same time, are ringed on the chart and listed in a table and in the Excel export.
  • Every export carries a title block, and the PDF fills an A3 or A1 landscape page. You can crop the chart to part of the route or the programme.

Your file is still read in your browser and never uploaded. Profiles saved from the earlier version still load.

New tool: Earthworks Haul Simulator

Watch every lorry load move from cut to fill along a road or rail scheme, and test how site constraints change the finish date before you commit to a plan.

Our first tool in a new group, Simulation systems. Planning the earthworks on a linear scheme means answering awkward questions: where should the soil from each cutting go, how many lorries will we need, and what happens to the finish date if a structure is late or the weather turns? The simulator works through the job one load at a time, so you can see the answers rather than guess them.

  • Describe the scheme as a row of sections, each with its length and how much soil it has spare or needs.
  • Press play and watch the loads move along the road, with a clock, a daily count and the number of lorries working.
  • Add the things that hold a site back: dates before which a fill cannot be tipped, closed roads, single-lane stretches, working hours, weekends and bank holidays.
  • Ask the optimiser for a better haul plan: the earliest finish, the best use of the daily limit or the shortest total haul. It shows the before and after side by side.
  • Run a weather and breakdown risk analysis for a 50% and 80% confidence finish date.
  • Turn on cost and carbon, see a time-chainage chart, and export the results, the daily totals and a programme you can import into P6 or Microsoft Project.
  • Seven worked examples let you try it before entering your own scheme.

This is an alpha release. The results are planning estimates for comparing options, not a contractor’s programme or a price. The cost, carbon and weather rates start as placeholders, and the tool marks every result that uses one until you enter your own. Everything runs in your browser and nothing is uploaded.

Which tools do people use? Our first four and a half months in numbers

Since July our tools have been opened 3,791 times. The XER Viewer leads, with the DCMA check and Schedule Mentor not far behind.

Since 7 July 2026, every time someone opens one of our tools, the site adds one to a simple counter for that tool. It records nothing about you and never sees your files. Here is what those counters show, up to 21 November.

ToolOpensShare
Online XER Viewer1,26233.3%
DCMA 14-Point Assessment86322.8%
Schedule Mentor54714.4%
Schedule Risk Analysis (QSRA-lite)2957.8%
XER Path Analyser2626.9%
Schedule Comparison & Milestone Slip1584.2%
Time-Chainage Chart1514.0%
Contractor Progress Roll-Up651.7%
Configuration State Map601.6%
EWN & Compensation Event Assistant431.1%
MS Project XML Importer & Fixer391.0%
XER Anonymiser340.9%
XER Cleaner120.3%

What stands out:

  • Opening a P6 file is the most common need. Almost half of all opens (48%) are for our two free starter tools, the XER Viewer and Schedule Mentor. Plenty of people are sent a P6 file without having P6 to open it.
  • Checking schedule quality comes next. The DCMA check, QSRA-lite, the Path Analyser and the Configuration State Map make up 39% between them. The DCMA check alone accounts for almost a quarter.
  • Reporting tools are used steadily. Schedule Comparison, Time-Chainage and Progress Roll-Up make up about 10%, which fits with monthly reporting cycles.
  • The specialist tools are for specific jobs. The file utilities and the EWN assistant add up to about 3%. You only need to clean, anonymise or convert a file now and then.
  • XER Cleaner has made a good start. It only went live on 5 November, but per day it is already opened more often than several tools that have been around since the summer.

A few words of caution. These are page opens, not people, so one planner opening a tool every morning counts many times. The figures also include our own testing, and newer tools have simply had less time to build up a count.

From today the counter also notes the day and hour of each open (still with nothing about who opened it), so in a future post we can look at which days of the week and which months are busiest. If a tool you use often is missing something, tell us.

XER Cleaner: better handling of calendars and multi-project files

A day after launch, XER Cleaner now keeps inherited holidays and copes with files that hold several projects.

Feedback on the first version of XER Cleaner pointed to three awkward cases. All three are now handled:

  • Inherited holidays are kept. In P6, a project calendar can borrow its holidays and non-working days from a company-wide calendar. When the cleaner turns global calendars into project calendars, it now copies those borrowed holidays across, so your working days do not quietly change.
  • Files with several projects. When two or more projects in one file share the same codes or calendars, each project now gets its own copy, so cleaning one does not affect the other.
  • Links to activities outside the file. Relationships to activities in projects that are not in the file are now dealt with separately, so the cleaned file still imports.

New tool: XER Cleaner

Clean up an XER from another organisation before you import it, so it does not fill your P6 database with their codes, calendars and resources.

When you import someone else’s XER into P6, it brings their company-wide data with it: activity codes, calendars, resources, user-defined fields and more. Over time this clutters your database and can clash with your own set-up. XER Cleaner tidies the file before it ever reaches P6.

  • Turns company-wide (global) codes and calendars into project-level ones, so they stay with the project.
  • Removes tables you do not need, and adds a prefix to resources and roles so you can tell where they came from.
  • Every change is a tick box, with three ready-made set-ups to start from: Standard clean, Strip everything and Minimal. You can also save your own.
  • A preview shows how many items each choice will change before you commit.
  • An integrity check runs before download, and you get a change log (CSV) of everything it did.
  • Cleans several files at once and gives you a single zip to download.

We still recommend importing the cleaned file into a test database first and checking it there.

Later updates: Better handling of calendars and multi-project files (6 November 2026).

An independent security review of the tools

We had every tool checked for security weaknesses and tightened the places where a badly made or harmful file could cause trouble.

Our clients often work on commercially sensitive and security-sensitive programmes, so we treat every file you open as untrusted. In August we put the whole toolkit through an independent security review and acted on what it found. In plain terms:

  • Saved settings files are checked more strictly when you load them back in.
  • Analyses that could run for a very long time on a deliberately awkward file are now stopped with a clear message, instead of freezing the page.
  • The XER Anonymiser’s report no longer shows the date shift or cost factor it used, so nobody can use them to reverse the disguise.

None of this changes how the tools look or work day to day. Your files are still processed only on your own computer.

Choose the text encoding yourself

If activity names look garbled, you can now tell any of our XER tools which character set the file uses.

Two days ago we taught the tools to recognise non-Roman alphabets automatically (see the previous post). Automatic guessing works well, but not every time. So every XER tool now has a small Text encoding menu next to the loaded file.

  • Leave it on Auto-detect and it shows you what it picked.
  • If names look wrong, choose another option: UTF-8, Western European, Cyrillic, Chinese (Simplified or Traditional), Japanese or Korean.
  • The file is re-read straight away, with nothing to reload.
  • In tools that take several files, such as Schedule Comparison, the choice applies to all of them.
  • The XER Anonymiser writes its output back in the same encoding, so the file still opens correctly in P6.

XER files in Cyrillic and other non-Roman scripts now open properly

Prompted by a user who sent us a Russian-language schedule, the tools now read Cyrillic, Chinese and Japanese activity names correctly.

An XER file does not say which character set it was saved in. P6 simply uses whatever the exporting computer was set to. Until now our tools assumed Western European, so a schedule exported on a Russian computer showed nonsense where the activity names should be.

A user got in touch with exactly this problem. We have changed the shared file reader used by every XER tool so it now looks at the file and works out the most likely character set itself:

  • Cyrillic (Windows-1251), as used for Russian, Ukrainian, Bulgarian and others.
  • Chinese, Simplified and Traditional.
  • Japanese.
  • Western European and UTF-8 files behave exactly as before.

Thank you to the user who reported it. If a tool ever shows garbled text from your file, please let us know.

Later updates: Choose the text encoding yourself (25 July 2026).

New tool: Configuration State Map

A tube-map style picture of every milestone that has to be achieved before each stage of a staged commissioning programme.

On rail, systems and nuclear work, a project often reaches its end state through a series of interim configurations. This tool asks a simple question of your P6 logic: what has to be done before we can reach each state? It then draws the answer as a map, with lines for each area of work and stations for each milestone.

  • Pick the milestones that mark each configuration state, put them in order and give them short names.
  • Choose an activity code or user-defined field to split the map into coloured lines.
  • Uses your schedule logic to decide what is needed, so the map follows the programme rather than opinion.
  • A checks panel lists likely problems, such as missing logic, prerequisites finishing too late and milestones with no code, and exports them as a to-do list.
  • Export as SVG, PNG, or a PDF sized for A3 or A1 printing.
  • Save your settings and reload them next period with the updated file.
  • A built-in sample programme lets you try it without your own file.

XER Path Analyser: export to PDF, SVG and PNG

You can now take the Path Analyser’s results straight into a report or presentation.

  • The Between two activities and Orphaned activities tabs have an Export PDF button. The PDF follows whatever search, sort and filters you have on screen.
  • The Path visualisation tab exports the network diagram as PDF, SVG (sharp at any size) or PNG (a picture you can paste anywhere).
  • Long diagrams are split neatly across pages in the PDF.

New tool: Contractor Progress Roll-Up

Roll a contractor’s detailed progress up onto your own summary programme, with every change shown for you to accept or reject.

If you hold a summary (Level 2) programme and your contractor reports progress against a detailed (Level 3 or 4) one, updating yours by hand each month is slow and easy to get wrong. This tool does the sums for you.

  • Load your programme and the contractor’s progressed programme. Baselines for either are optional and add extra checks.
  • Link each of your activities to a stretch of the contractor’s programme, using a start activity and an end activity.
  • For each of your activities it works out percent complete, actual start and remaining duration on your calendar.
  • Choose how percent complete is weighted, for example by duration or by a contractor field.
  • A coverage view shows contractor work you have not linked to anything.
  • Review every change, then download an updated XER containing only what you accepted, plus a CSV record of your decisions.
  • Save your links and reuse them next month.

QSRA-lite: enter ranges in working days, and clearer charts

Planners can now enter risk ranges in working days instead of percentages, and the tornado charts come with a colour key.

  • Percentage or working days. A new switch above the review table lets you show and type the optimistic, most likely and pessimistic ranges in working days. The tool converts them for you.
  • Duration column. Each activity now shows its duration in working days, so you can see what a range applies to.
  • Colour key for the tornado charts, on screen and in the PDF, explaining what the blue and green bars mean.
  • Relationship lags flagged. The results now warn you how many lags and leads the schedule contains, because these are not risk-ranged and can distort the result.
  • Fixed a fault where edits to individual activity ranges could be lost, and added a short note explaining what saving and loading a profile does.

Saved settings files now have sensible names

Settings files saved from the tools are now named with the date, the schedule they came from and what they are.

Several tools let you save your settings and load them again next period. Those files used to have generic names, which made them hard to find later. They are now named like this:

2026-07-08 - City Road Rev C - QSRA Lite Values & Settings.json

This applies to QSRA-lite, the XER Anonymiser, Time-Chainage, DCMA 14-Point, Schedule Comparison and the EWN & Compensation Event Assistant.

Clearer, more consistent PDF reports

Every report the tools produce now shares one tidy layout, and the QSRA-lite report gains its charts.

  • Reports from QSRA-lite, Schedule Mentor, the EWN & Compensation Event Assistant, DCMA 14-Point and Schedule Comparison now share the same clean style, with clear headings and tables that repeat their headers across pages.
  • The QSRA-lite PDF now includes the confidence S-curve, a table of the dates you are watching, and both tornado charts showing which activities drive the risk.
  • Duplicated tables have been removed from the QSRA-lite report so it is shorter and easier to read.

New tool: EWN & Compensation Event Assistant

Compare the accepted programme with the current one, explain what has grown, and draft NEC early warnings and compensation event notices.

The tool finds where the work has grown in time, scope or cost between your accepted baseline and your current programme. You decide the cause of each item in your own words, and it drafts the notices. It never decides what is claimable; that stays with you.

  • Load the accepted baseline and the current programme, plus an optional interim update to show when each change first appeared.
  • Works for NEC4, NEC3 or a generic contract without clause references.
  • Finds candidate items such as new scope, longer activities, removed work, cost growth and movement in milestones or Completion.
  • Split an item into parts with different causes, and record the event type, dates, days and cost for each.
  • Draft early warning notices, compensation event notifications or both, and edit them.
  • Export each notice to PDF, or all of them together, and the event register to Excel or CSV.
  • An optional AI mode can reword the drafts. It runs on your own computer and only sees the facts for that item.

Later updates: clearer PDF notices (7 July 2026), named settings files (8 July 2026), text encoding choice (25 July 2026).

New tool: Online XER Viewer

Open a Primavera P6 XER file as a clear Gantt chart in your browser, free, with no P6 licence needed.

Clients, commercial teams, quantity surveyors and lawyers are often sent a P6 file but have no way to open it. The XER Viewer shows it as a familiar bar chart. It only reads the file and never changes it.

  • Activity list grouped by WBS on the left, Gantt chart on the right, with the critical path in red.
  • Choose which columns to show, including dates, float, constraints, links, codes and resources.
  • Filter by text, status, critical only, milestones, a date window, a WBS branch or float below a number of days.
  • Click any bar to see every detail of that activity and its links.
  • Print to PDF on A4 or A3, with headers repeated and pages numbered.
  • Export the table to CSV, or the chart to PNG or SVG.
  • Copes with large schedules of tens of thousands of activities.

Later updates: non-Roman scripts (23 July 2026), text encoding choice (25 July 2026).

New tool: Schedule Mentor

A friendly, free review of your P6 schedule that teaches you what to fix and why, using examples from your own file.

Schedule Mentor is aimed at planners who are still learning. Instead of a pass or fail score, it walks you through your schedule one lesson at a time, the way an experienced colleague would. Nobody else sees the results.

  • Around twenty short lessons covering logic, constraints, calendars and durations, progress and structure.
  • Each lesson shows what it spotted (with your real activity IDs), why it matters, how to fix it in P6, and when it is actually fine.
  • Starts with what you are doing well, and labels each point by how much it matters.
  • Fix things in P6, load the new file, and see a before and after for each lesson.
  • Download a PDF study sheet to keep.
  • You can browse the lessons without loading a file.

Later updates: clearer PDF reports (7 July 2026), non-Roman scripts (23 July 2026), text encoding choice (25 July 2026).

New tool: XER Path Analyser

Find every activity that links two points in your schedule, and spot activities that do not lead anywhere.

  • Between two activities: pick a start and an end activity and see every activity on the logic paths between them. Filter to critical only or to one WBS branch.
  • Orphaned activities: lists activities with no route through to the end of the project, a common sign of missing logic.
  • Path visualisation: an interactive network diagram, read left to right, with the critical path in red. Zoom, pan and click for details.
  • Sort, search and export the tables to CSV.
  • Warns about circular logic instead of getting stuck.

Later updates: PDF, SVG and PNG exports (23 July 2026), text encoding choice (25 July 2026).

New tool: DCMA 14-Point Assessment

Run the well-known 14-point schedule health check on a P6 file and print an assurance report.

The DCMA 14-point assessment is a standard set of checks for schedule quality, such as missing logic, too many constraints and very long durations. This tool runs all fourteen in seconds.

  • A dashboard of fourteen tiles, coloured red, amber or green, with shapes as well as colours so it works for colour-blind users.
  • Click a tile for a plain-English explanation and the list of activities that failed, which you can export to CSV.
  • Adjust any threshold to suit your contract, and record why. The report shows every change from the standard.
  • Optionally load a second file as the baseline.
  • Save your thresholds as a profile and reuse them.
  • Print a tidy assurance report to PDF.

Later updates: clearer reports (7 July 2026), named settings files (8 July 2026), text encoding choice (25 July 2026).

New tool: Schedule Risk Analysis (QSRA-lite)

See how much confidence your planned finish date really deserves, and which activities drive the risk.

QSRA-lite runs a Monte Carlo simulation on your P6 network. In simple terms, it replays the schedule thousands of times with durations varied within ranges you set, then tells you how often the plan date is met. It is a quick screening check, not a full risk analysis.

  • First checks that it can reproduce your schedule’s own dates, and shows how close the match is.
  • Set duration ranges for the whole schedule, a WBS area, an activity code or a single activity.
  • Results as an S-curve and histogram with P50, P80 and other confidence levels, for example “your plan date is P34”.
  • Tornado charts show the activities that drive the risk most.
  • Optional simple risk events and an overall correlation setting.
  • Export the chart, a CSV of risk drivers, a PDF summary and your settings.

Later updates: charts in the PDF report (7 July 2026), ranges in working days (8 July 2026), text encoding choice (25 July 2026).

New tool: Schedule Comparison & Milestone Slip

Compare your baseline, current and interim schedules, see which milestones have slipped, and get a factual draft narrative for your report.

  • Load two or more XER files. They are put in date order for you, and activities are matched by activity ID.
  • Group milestones as Mandatory, Contract, Key or Tracked, using an activity code, a user-defined field, an ID pattern or a simple tick list.
  • Milestone slip tables, a critical path comparison, a change register (added, deleted, logic, durations, constraints and calendars), float erosion, progress this period, and slip by WBS.
  • The classic milestone slip chart, exportable as PNG or SVG.
  • A factual draft narrative you can edit before it goes into your report. An optional AI drafting mode runs on your own computer; your schedule is never sent anywhere.
  • Add your own header and logo, then print the report to PDF.
  • Save your set-up and reload it next month.

Later updates: clearer reports (7 July 2026), named settings files (8 July 2026), text encoding choice (25 July 2026).

New tool: Time-Chainage Chart

Turn a P6 schedule for linear works into a time-location chart that shows where and when each team is working.

On railways, roads, pipelines and tunnels, a bar chart hides the most important question: will two crews be in the same place at the same time? A time-chainage chart answers it at a glance.

  • Reads chainage from a user-defined field, an activity code or a pattern in the activity ID or name.
  • Works in metres, kilometres, km+m (for example 12+400) or miles and chains.
  • Colour by WBS, activity code or critical path, and swap or flip the axes.
  • Show the data date, named locations and possession periods, and optionally a faint copy of the baseline.
  • Shows how many activities it could place, and lists the rest for you to check.
  • Export to PNG, SVG, PDF or an Excel workbook.
  • A demo scheme lets you try it before using your own file.

Later updates: named settings files (8 July 2026), text encoding choice (25 July 2026).

New tool: XER Anonymiser

Remove or disguise names, resources, costs and notes in a P6 file so you can share it safely, while keeping the logic and dates.

  • For each type of information, choose whether to keep it, blank it out or replace it with consistent stand-in names.
  • Costs can be kept, set to zero or scaled. All dates can be shifted by a set number of days without changing durations or float.
  • Activity IDs, logic, durations, float, percent complete and calendars are never touched.
  • A final scan looks for anything left behind, including your own sensitive words, email addresses, phone numbers and postcodes.
  • Preview before and after, then download the cleaned XER and a short report.
  • Save the name mapping so next month’s file gets the same stand-in names.

Later updates: named settings files (8 July 2026), text encoding choice (25 July 2026), security review (23 August 2026).

New tool: MS Project XML Importer & Fixer

Fix the problems that make a Microsoft Project file fail or go wrong when you import it into P6.

Importing a Microsoft Project schedule into P6 often fails, or seems to work but quietly loses information. This tool checks the Microsoft Project XML file first and repairs the known causes.

  • A dry run lists every problem it finds before anything is changed.
  • Safe repairs are switched on by default. Riskier changes are off by default and come with a warning.
  • Duplicate activity IDs are renumbered so they do not clash in P6.
  • Download a fixed XML file, a PDF report of every change and a CSV list of changes.
  • An experimental XER is also produced, which you can open straight away in our XER Viewer.

On 7 July we renamed it from “MS Project XML Fixer” to reflect that it also imports and views the schedule.