Configuration State Map

Tube-map milestone diagrams for staged commissioning, 100% in your browser, nothing uploaded.
Drop a .xer file here, or click to choose
Oracle Primavera P6 XER export
🔒 Parsed entirely in your browser, no server, no upload, no storage.

Configuration state maps for staged commissioning

In staged commissioning environments — rail, systems, nuclear — a programme moves through configuration states executed strictly in order, and each state has a set of milestones that must be achieved before it can be declared. This tool reads your P6 XER, traces the schedule logic behind each designated state, and draws the answer as a one-page schematic in the visual language of the London Underground map: coloured swimlanes of milestones running into the configuration state line.

"Required" here means a predecessor path exists in the schedule network — traced through ordinary activities, not just direct links, and deliberately not P6's driving-path flag.

More Primavera P6 tools