Milestone slip chart

Drop in a series of Primavera P6 XER files, one for each monthly update of the same project, and get a milestone slip chart: each file's data date across the page and the forecast date of each milestone up the page. A flat line means the forecast is holding. A rising line means it is moving later. A line that reaches the diagonal is a milestone that has been achieved.

🔒 Your files are read in your browser and never uploaded.

1. Your files

Drop your XER files here, or press Enter to choose them. Add all the updates at once, or add more later.

Help

Add the XER of each monthly update. Files are sorted by their data date. Each milestone becomes a line: its forecast date in each file, plotted against that file's data date.

Keyboard: Tab moves between points on the chart; the details of the focused point appear above it. Escape closes this window.

How to read a milestone slip chart

A milestone slip chart, also called a milestone trend chart, shows how the forecast date of a milestone has changed from one programme update to the next. The horizontal axis is the reporting date: the data date of each update. The vertical axis is the forecast date of the milestone in that update. Each update adds one point to the milestone's line.

Dates and movement are shown in calendar days by default, with working days on each milestone's own calendar as an option. Positive movement means later. The tool reports what the schedules show. It does not state or imply a cause.

Questions

Do my files have to be the same project?

Yes: the files should be successive updates of one project. Updates are normally separate copies in P6 with their own project IDs and short names, so those are not compared. The tool matches milestones by Activity ID and warns if a file shares fewer than half of its Activity IDs with the others.

Which date is plotted for each milestone?

The actual date if the milestone has been actualised in that file, otherwise the early (forecast) date. A finish milestone uses its finish and a start milestone its start. If a file has no early date, the target date is used and the checks table says so.

What is a baseline here?

An ordinary update that you tag as a baseline. It still adds a point to every line. Points from baseline files are outlined: one style for the current baseline and another for earlier ones. If you tag nothing, the earliest file is treated as the baseline and the chart says so.

Is anything uploaded?

No. Your files are read in your browser. Nothing is sent to a server and nothing is stored.

What can I export?

PNG, SVG and PDF, in A4 or A3 landscape or portrait, all drawn from the same chart you see on screen. Excel and CSV for the dates and movement, and a settings file you can load again.

More Primavera P6 tools