Drop in a series of Primavera P6 XER files, one for each monthly update of the same project, and get a milestone slip chart: each file's data date across the page and the forecast date of each milestone up the page. A flat line means the forecast is holding. A rising line means it is moving later. A line that reaches the diagonal is a milestone that has been achieved.
🔒 Your files are read in your browser and never uploaded.
1. Your files
Drop your XER files here, or press Enter to choose them. Add all the updates at once, or add more later.
Files are plotted in order of reporting date (the XER data date unless you override it). Tag a file as a baseline to outline its points on the chart.
Loaded files
Use
File
Project
Data date
Reporting date
Period label
Baseline
Milestones
Remove
Period
2. Milestones
Milestones found in the files
Chart
ID
Name
WBS
Type
Files
Chart settings for each selected milestone
ID
Name on chart
Colour
Marker
Line
Contract date
Highlight
Matching milestones across files (0)
Milestones are matched by Activity ID. If an ID was renumbered, join the two here. Suggestions are never applied until you confirm them.
3. Chart
Chart options
Axes
Baselines
Show on chart
Event annotations
Reporting date
Text
Remove
Title block
ExportProfile
4. Dates, movement and checks
Also show:
Summary per milestone
Checks
How to read a milestone slip chart
A milestone slip chart, also called a milestone trend chart, shows how the forecast date of a milestone has changed from one programme update to the next. The horizontal axis is the reporting date: the data date of each update. The vertical axis is the forecast date of the milestone in that update. Each update adds one point to the milestone's line.
A flat line means the forecast has held. It is worth checking the float: a flat line can hide negative float, or a constraint that is holding the date in place. The tool marks both.
A rising line means the forecast has moved later. A falling line means it has moved earlier.
The diagonal is where the forecast date equals the reporting date. A date cannot be forecast earlier than the data date, so the area beyond the diagonal is shaded. When a milestone is actualised, its line runs to the diagonal at the actual date and stops.
Dates and movement are shown in calendar days by default, with working days on each milestone's own calendar as an option. Positive movement means later. The tool reports what the schedules show. It does not state or imply a cause.
Questions
Do my files have to be the same project?
Yes: the files should be successive updates of one project. Updates are normally separate copies in P6 with their own project IDs and short names, so those are not compared. The tool matches milestones by Activity ID and warns if a file shares fewer than half of its Activity IDs with the others.
Which date is plotted for each milestone?
The actual date if the milestone has been actualised in that file, otherwise the early (forecast) date. A finish milestone uses its finish and a start milestone its start. If a file has no early date, the target date is used and the checks table says so.
What is a baseline here?
An ordinary update that you tag as a baseline. It still adds a point to every line. Points from baseline files are outlined: one style for the current baseline and another for earlier ones. If you tag nothing, the earliest file is treated as the baseline and the chart says so.
Is anything uploaded?
No. Your files are read in your browser. Nothing is sent to a server and nothing is stored.
What can I export?
PNG, SVG and PDF, in A4 or A3 landscape or portrait, all drawn from the same chart you see on screen. Excel and CSV for the dates and movement, and a settings file you can load again.